View Case Filings for: 2019-00145
Service Type:Gas
Filing Date:5/9/2019
Category:Regular
Utilities:
Atmos Energy Corporation
Case Nature:
Special Contract with Diageo Americas Supply, Inc.
Case Filings | |
---|---|
Filing | Documents |
1/21/2020 2:36:35 PM
Order Entered: 1. Atmos's July 1, 2019 petition, as amended, for confidential protection is granted. 2. The designated materials shall not be placed in the public record or made available for public inspection for an indefinite period, or until further Orders of this Commission. 3. Use of the designated materials in any Commission proceeding shall be in compliance with 807 KAR 5:001 , Section 13(9). 4. Atmos shall inform the Commission if the designated materials become publicly available or no longer qualify for confidential treatment. 5. If a non-party to this proceeding requests to inspect the designated materials granted confidential treatment by this Order and the period during which the materials have been granted confidential treatment has not expired, Atmos shall have 30 days from receipt of written notice of the request to demonstrate that the materials still fall within the exclusions from disclosure requirements established in KRS 61.878. If Atmos is unable to make such demonstration, the requested materials shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. 6. The Commission shall not make the designated materials available for inspection for 30 days following an Order finding that the materials no longer qualify for confidential treatment in order to allow Atmos to seek a remedy afforded by law. |
|
9/24/2019 10:34:45 AM
Final Order Entered: 1. The special contract between Atmos and Diageo reapproved effective October 1, 2019. 2. By March 31 of each year, Atmos shall file an annual report with the Commission detailing, for the prior calendar year, revenues received from Diageo and the marginal costs associated with serving Diageo throughout the term of the special contract. 3. During any rate proceedings filed by Atmos subsequent to the effective date of the special contract with Diageo, and during a period when Atmos still has an active EDR contract, Atmos shall demonstrate through detailed cost-of-service analysis that its non-EDR ratepayers are not adversely affected by the EDR rate to Diageo and any other EDR customers that may be on the Atmos system at that time. 4. Atmos shall file by March 31 of each year a report with the Commission providing, for the prior calendar year, the information shown in the Appendix to this Order. 5. Any documents filed pursuant to Ordering paragraphs 2 and 4 of this Order shall reference the number of this case and shall be retained in the utility's general correspondence file. 6. The Executive Director is designated authority to grant a reasonable extension of time for the filing of any documents required by this Order upon Atmos's showing of good cause for such extension. 7. Within 20 days of this Order, Atmos shall file the special contract as approved herein. 8. This case is closed and removed from the Commission's docket. |
|
8/27/2019
Atmos Energy Corporation Response to Attorney General Motion to Substitute Supplemental Data Requests and Submit Case on the Record |
|
8/22/2019
Attorney General Notice of Filing- Submission on the Record |
|
8/22/2019
Attorney General Motion to Substitute Supplemental Data Requests to Atmos Energy Corporation |
|
7/29/2019
Atmos Energy Corporation Response to Attorney General Supplemental Data Request |
|
7/25/2019
Atmos Energy Corporation Response to Attorney General Objection to Petition for Confidentiality and Amended Petition |
|
7/18/2019
Attorney General Objection to Atmos Energy Corp. Petition for Confidentiality |
|
7/15/2019
Atmos Energy Corporation Response to Commission Staff Second Request for Data |
|
7/15/2019
Attorney General Supplemental Data Requests to Atmos Energy Corporation |
|
7/11/2019 9:52:24 AM
Commission Staff's Second Request for Information to Atmos Energy Corporation |
|
7/10/2019
Atmos Energy Corporation Redacted Response to Commission Staff First Request for Data |
|
7/1/2019
Atmos Energy Corporation Response to Attorney General First Request for Data |
|
7/1/2019
Atmos Energy Corporation Response to Commission Staff First Request for Data with Petition for Confidential Treatment |
|
6/17/2019
Attorney General Initial Data Request |
|
6/14/2019 11:10:22 AM
Commission Staff's Initial Request for Information to Atmos Energy Corporation |
|
6/13/2019
Attorney General Notice of Waiver of Service by U.S. Mail |
|
5/30/2019 11:56:04 AM
Order Entered: 1. The motion of the Attorney General to intervene is granted. 2. The Attorney General shall be entitled to the full rights of a party and shall be served with the Commission's Orders and with filed testimony, exhibits, pleadings, correspondence, and all other documents submitted by parties after the date of this Order. 3. The Attorney General shall adhere to the procedural schedule set forth in the Commission's May 21, 2019 Order and as amended by subsequent Orders. 4. Pursuant to 807 KAR 5:001, Section 8(9), within seven days of entry of this Order, the Attorney General shall file a written statement with the Commission that: a. Certifies that it, or its agent, possesses the facilities to receive electronic transmissions; and b. Sets forth the electronic mail address to which all electronic notices and messages related to this proceeding should be served. |
|
5/21/2019 10:49:29 AM
Order Entered: 1. The procedural schedule set forth in the Appendix to this Order shall be followed in this proceeding. 2. a. Responses to requests for information shall be appropriately bound, tabbed, and indexed and shall include the name of the witness responsible for responding to the questions related to the information provided, with copies to all parties of record, the original and six copies to the Commission. b. Each response shall be answered under oath, or for representatives of a public or private corporation or a partnership or an association or a governmental agency, be accompanied by a signed certification of the preparer or person supervising the preparation of the response on behalf of the entity that the response is true and accurate to the best of that person's knowledge, information , and belief formed after a reasonable inquiry. c. Any party shall make timely amendment to any prior response if it obtains information which indicates that the response was incorrect when made or, though correct when made, is now incorrect in any material respect. d. For any request to which a party fails or refuses to furnish all or part of the requested information, that party shall provide a written explanation of the specific grounds for its failure to completely and precisely respond. |
|
5/16/2019
Attorney General's Motion to Intervene |
|
5/9/2019 3:09:00 PM
Acknowledge Receipt of Filing |
|
5/9/2019
Atmos Energy Corporation Application for Approval of a Special Contract Pursuant to Its Economic Development Rider |