1/22/2019 12:40:53 PM
Final Order Entered: 1. AT&T Mobility is granted a CPCN to construct a wireless telecommunications facility. The proposed facility consists of a tower not to exceed 270 feet in height, with attached antennas, to be located at 544 Adaburg Tower Lane, Hartford, Ohio County, Kentucky. The coordinates for the proposed facility are North Latitude 37°35'25.53" by West Longitude 86°51'29.35". 2. AT&T Mobility shall immediately notify the Commission in writing if, after the antenna tower is built and utility service is commenced, the tower is not used for a period of three months in the manner authorized by this Order. 3. AT&T Mobility shall file a copy of the final decision regarding the pending
FFA and KAZC applications for the proposed construction within ten days of receiving a decision. 4. Documents filed, if any, in the future pursuant to ordering paragraphs 2 and 3 shall reference this case number and shall be retained in the post-case correspondence
file. 5. This case is closed and removed from the Commission's docket.
|
|